 Day 1- Roof tiles are stripped and temporary weather protection is applied to the roof, and new floor structure is put in place inside the existing roof structure. 

 
 

 Day 2- New floor is then decked using 18mm egger protect decking with the existing roof remaining on. 

 
 

 Day 3- The existing roof is now removed and a temporary weather protection membrane is placed over the new floor structure, and the new first floor structure and roof is erected.

 
 

 Day 3- The new roof structure begins to take shape using pre-manufactured roof trusses. 

 
 

Day 5- Structural roofing works continue with roof structure to be completed in a further two days, ready for roof finish to be applied.

 
 

Day 8- Roofers and window fitters carry out their works and the property is in the dry and secure ready for all following trades.

 

                       Completed Project... 