Top Hat Extension, Swanland...
All services are stripped out prior to the arrival of Sms Timber Frame for safety reasons. | All roof tiles were also removed prior to the arrival of Sms Timber Frame. |
Day 1- The new floor structure if fitted and decking is applied to as much of the floor as possible with the roof remaining in tact, all ceilings are saved. | Day 2- The roof is now stripped off progressively over the course of one morning to allow our team to completed the new floor structure. |
Day-2 The floor structure is completed and ready to accept temporary weather membrane. | Day 2- The weather membrane is applied to ensure water ingress is kept to a harmless minimum and save all ceilings. |
Day 4- New structure is erected ready to accept pre-manufactured trusses. | Day 6- With the new first floor structure in place, the complex roof begins to take shape, and is completed in the following two days. |
Completed Project...